Policy and tariff
If your state ends net metering, what happens to your system
Grandfathering is real, it is time-limited, and in at least one tariff it does not belong to the house.
Written by HyreSolar Research team Research and analysis
Audited by HyreSolar Research team Data audit and fact check
The short answer
Existing customers are usually protected, and the protection has a shape
The fear when a state changes its solar tariff is that a system already on the roof will be switched to the new terms overnight. In the transition we read in detail, that is not what happened, and the decision is explicit: "The Commission finds that the NEM 1.0 and NEM 2.0 tariff should remain intact."
The protection is a defined legacy period. An earlier decision had established twenty years from the customer's interconnection as the period over which a customer should remain eligible for the earlier tariff, with a stated rationale worth quoting because it is the case for grandfathering generally: to "allow customers to have a uniform and reliable expectation of stability of the net energy metering structure under which they decided to invest".
But read what the same decision says about its own authority. It concluded that the Commission "has the authority to revise the legacy NEM 1.0 and NEM 2.0 tariffs", and declined to do so because the outcome "could result in an inequity to one of two groups". It did not decline because it could not.
That distinction matters if you are relying on a legacy period. It was a policy choice, made by a body that had recorded that it could choose otherwise, and it was contested. Parties in that proceeding proposed moving existing customers onto new rates at five years from interconnection, and at eight years. Both were rejected. They were also seriously argued.
The legacy period covers less than people assume
Two limits are stated in the decision and both catch people out.
It covers the tariff, not the bill. The decision restates that the twenty-year period "applies only to service under the net energy metering successor tariff, not to any other aspect of the customer's bill, for example a minimum bill". Fixed charges and other elements were dealt with in a separate proceeding entirely. Being grandfathered on your export arrangement does not freeze what you pay overall.
And on the successor tariff it is narrower still. Its own legacy provision reads: "With the exception of the import rate itself, the adopted successor tariff elements… will be available to an enrolled customer for a period of nine years from the interconnection date."
Read the exception. The rate you pay to buy electricity is expressly outside the lock. Only the export-side terms are protected. So a customer can be fully within their legacy period and still see the cost of the electricity they import change.
Nine years, and the request to make it longer was refused
The successor tariff's legacy period is nine years from interconnection, against twenty on the tariff it replaced. That is a substantial reduction and it was argued about.
Parties asked for fifteen. The Commission kept nine, and its stated reasoning is worth knowing because it tells you something about how these periods are set: the avoided cost calculator that determines export rates "is a forecast and, therefore, its values become increasingly uncertain as time moves away from the present".
In other words, the length of your protection was set by how far ahead the regulator was willing to commit to a forecast. That is a defensible position and it is not a promise about your system's economics over its life. A twenty-five-year asset now carries a nine-year guarantee on the terms that determine what it earns.
That gap between the asset's life and the guarantee's length is the single most useful thing on this page for anyone running numbers. It does not mean the export terms will worsen at year ten; the regulator has made no such statement and we are not predicting one. It means that the last sixteen years of a twenty-five-year projection rest on an assumption rather than on a commitment, and a projection that does not say which is which is not telling you how much of its own answer is guaranteed.
The legacy period belongs to you, not to your roof
The legacy period is the provision that most surprises people, and it is stated plainly in the decision.
"This decision clarifies that the legacy period is linked to the customer who originally causes the system to be installed, not to the system itself. If the original customer moves away within nine years from the system's interconnection date and another utility customer takes control of (e.g., buys, leases, or pays a power purchase agreement for) the system, the subsequent utility customer does not have a legacy period."
Work through what that means when you sell. You interconnect in year one and move in year four. Your buyer inherits the panels, the inverter, the warranties and the roof penetrations. They do not inherit your export terms. They take service on whatever tariff applies to them at that point, with no legacy period at all.
There is one exception and it is narrow. A legal partner, meaning a spouse or domestic partner for a residential customer, may continue it. Even then the decision is explicit that "the legacy period does not restart… the legacy period maintains its original interconnection date and length of nine years". The utilities were directed to create a uniform attestation for this.
The solar industry made exactly the objection you would expect, on the record: tying the legacy period to the customer rather than the system "breaks with current policy and may impact the value of a home". The Commission did not change course.
Which makes this a home-value question as much as a tariff question
The legacy provision connects directly to something we cover elsewhere, and the connection is not obvious until you see it.
Research on solar and resale value found premiums falling sharply as systems age, and separately found no significant premium for third-party-owned systems. A legacy period that expires on sale adds another mechanism pointing the same way: part of what a solar home is worth to its current owner is a tariff arrangement the buyer cannot have.
We are not going to quantify that, because nobody has and we found no source attempting it. The industry asserted an effect on home value in a regulatory filing, which is an interested party's argument rather than evidence.
But it is a real consideration in two directions. If you are selling, do not assume the buyer inherits your economics, and do not let a listing imply they will. If you are buying, ask specifically what tariff you would take service on, because it may not be the one the seller has been enjoying, and the savings history you are shown may not be repeatable.
The vocabulary of grandfathering
- Legacy period
- The defined length of time an existing customer may continue taking service under a tariff that has since closed to new applicants. It runs from a specified event, which in the cases we read is the interconnection date rather than the contract date.
- Interconnection date
- The date your system was connected and authorised. It is the clock-start for a legacy period, which is why it matters more than the date you signed or the date installation finished.
- Import rate
- What you pay for electricity you draw from the grid. Expressly excluded from the successor tariff’s legacy lock, so it can change while you are still protected on the export side.
- Closed to new enrollments
- A tariff that still serves its existing customers but accepts no new ones. This is the normal shape of a transition: the old regime is not abolished, it stops taking applicants and then ages out.
- Legal partner
- The narrow exception to the rule that a legacy period ends when the original customer leaves. For a residential customer this means a spouse or domestic partner, and even then the period does not restart.
- Avoided cost calculator
- The model that sets export rates under the successor tariff. Its forecast nature was the stated reason for limiting the legacy period to nine years rather than fifteen.
The two legacy regimes, side by side
| The earlier net metering tariffs | The successor net billing tariff | |
|---|---|---|
| Legacy period | 20 years from interconnection | 9 years from interconnection |
| Where it came from | An earlier decision, on a stability rationale | The adopting decision; a 15-year request was refused |
| What it covers | Service under the tariff only, expressly not other bill elements such as a minimum bill | The successor tariff elements, expressly excluding the import rate |
| Does it survive a sale? | Not addressed in the passages we read | No. It is linked to the customer, not the system |
| Who can inherit it | Not addressed in the passages we read | A legal partner only, and it does not restart |
| Could the regulator revoke it? | It concluded it has the authority and declined on policy grounds | Not addressed |
From the adopting decision, read 3 September 2026. Blank cells are genuinely not addressed in the sections we read rather than absent from the decision.
The row worth acting on is the sale row. On the successor tariff, the legacy period is a personal entitlement that ends when you move, and neither the panels nor the address carries it forward.
What to do about it
- 1 Find out which tariff you are actually on, and your interconnection date
Legacy periods run from interconnection, so that date is the one that matters rather than when you signed or when installation finished. Your utility can confirm both.
- 2 Find out how long your protection runs and what it covers
Ask specifically whether it covers the import rate. In the successor tariff we read it does not, so a customer inside their legacy period can still see the price of electricity they buy change.
- 3 If you plan to sell inside that window, find out whether it transfers
On the tariff we read it does not, and only a spouse or domestic partner may continue it. That is a fact to establish before you list, not during a negotiation.
- 4 If you are buying a house with solar, ask what tariff you would be on
Not what the seller is on. The seller’s bills may reflect an arrangement you cannot have, which makes their savings history a poor guide to yours.
- 5 Do not model twenty-five years of savings on a nine-year guarantee
A payback calculation that assumes today’s export terms for the life of the system is assuming something no regulator has promised. Ask what the model assumes after the legacy period ends.
- 6 Treat proposed legislation as proposed
Bills that would change legacy rules circulate widely and are frequently described as though enacted. Check the status on the legislature’s own site before acting on anything you read about a pending change.
Method and limitations
What was read
The adopting decision in full for the passages quoted: the finding that the earlier tariffs should remain intact, the twenty-year legacy period and its rationale, the Commission's conclusion that it has authority to revise legacy tariffs, the five-year and eight-year proposals that were rejected, the limit of the legacy period to the tariff rather than the whole bill, the nine-year successor legacy period with the import rate expressly excluded, the refusal of a fifteen-year extension and its reasoning, and the provision linking the legacy period to the customer rather than the system together with the legal-partner exception.
One state, and the limit that puts on this page
Everything specific here comes from one state's decision. We could not reach a primary source for any second state's treatment of legacy customers, and we name none.
What generalises is the set of questions rather than the answers: how long, covering what, and does it survive a sale. Those three are worth asking wherever you are, and your own commission's decisions are public documents.
Two things we deliberately do not state
A pending California bill that circulates as if it were law. It would have required a buyer of a property with an existing system to take service on the current tariff rather than the seller's legacy one. Its status page shows it stalled in a Senate committee with no action after 29 August 2025. It is a proposal that did not pass, and we mention it here only because it is widely described otherwise.
A claim about Nevada. A reversal there appears in the record of this proceeding as an argument made by parties. We have not verified the underlying facts and do not repeat them as established.
Not legal or financial advice
This describes a regulatory decision. What applies to you depends on your state, your utility, your tariff and your interconnection date. Your commission publishes its decisions, and your utility can confirm your own dates in a phone call.
Questions
If my state ends net metering, do I lose it?
How long does grandfathering last?
Does my legacy period protect what I pay for electricity?
Does the legacy period transfer when I sell my house?
Does that affect what my house is worth?
Can a regulator take away a legacy period it already granted?
Should I rush to install before rules change?
What should a payback calculation assume after the legacy period ends?
Written and audited by
HyreSolar Research
Primary-source research, data analysis and fact checking
We are a research desk, not a sales floor. We read the statute, the tariff, the code section, the federal filing or the manufacturer data sheet ourselves, and we publish the figure with the document it came from and the date we retrieved it. Where a number cannot be traced to a primary source, we publish the shorter page and say what we could not verify. That rule has cost us whole sections, and it is the reason the rest can be trusted.
- 160
- primary sources read and cited
- 220
- figures with a retrieval date
- 115
- federal and state government sources
- 66
- researched pages published
How this desk works
- Primary sources only. Statutes from the legislature’s own publishing system, federal data from the agency that collects it, code text from the adopted edition, manufacturer claims from the data sheet. We do not cite an article that cites a source; we go and read the source.
- Every figure carries its provenance. A named document and the date we retrieved it, so you can check it and so you know how old it is. Retrieval dates are not decoration: an EIA rate from May is a different fact from an EIA rate from August.
- We publish what we could not verify. Every research page carries a section naming the things we tried to establish and could not, and why. A paywalled standard, a state website that refused the request, a manufacturer that publishes no figure at all.
- We separate measurement from modelling from our own reasoning, and label which is which on the page. A laboratory measurement, an assumption inside a modelling tool and our own inference are three different kinds of claim and they are never presented as one.
- We do not sell solar, and we take no payment for placement, ranking or a favourable mention. Nobody buys a position on this site.
Data as of The adopting decision read on 3 September 2026. Authorship on this site is organisational: the analysis belongs to the desk rather than to a named individual, and we do not publish credentials we do not hold. Our editorial policy sets out how we source, date and correct what we publish.
Sources & retrieval dates
- CPUC Decision 22-12-056: Decision Revising Net Energy Metering Tariff and Subtariffs — Adopted 15 December 2022. Source for every quotation on this page: that the earlier tariffs should remain intact, the twenty-year legacy period established by an earlier decision and its stability rationale, the Commission’s conclusion that it has authority to revise legacy tariffs, the rejected five-year and eight-year transition proposals, the limitation of the legacy period to the tariff rather than other bill elements such as a minimum bill, the nine-year successor legacy period excluding the import rate, the refusal of a fifteen-year extension and the forecast-uncertainty reasoning behind it, the provision linking the legacy period to the customer rather than the system, the legal-partner exception and the direction to create a uniform attestation, and the industry’s recorded objection that the change may impact the value of a home. Retrieved 3 September 2026.
- California Legislative Information, AB-942 bill status — Cited only to establish that a widely discussed bill affecting legacy tariffs on sale of a property did not pass. The status page shows it referred to a suspense file in August 2025 and re-referred to a Senate committee on 29 August 2025, with no action after that date. Retrieved 3 September 2026.
Selling or buying a house with solar on it?
Tell us the utility and the interconnection date. We will tell you what legacy protection exists, how long it runs, and whether it survives the sale.
HyreSolar is an independent analysis and matching service. We are not an installer, lender or utility. When a reader asks to be introduced, installers may pay us a referral fee. That fee never buys ranking, scores or placement in research. Our editorial policy sets out the rules.