Additional
What a critical load panel is, and why you need one
A second, smaller electrical panel holding the circuits that keep working when the grid does not.
Written by HyreSolar Research team Research and analysis
Audited by HyreSolar Research team Data audit and fact check
The short answer
Why a house cannot simply run on a battery
The intuition is that a battery holds energy and a house uses energy, so a big enough battery runs the house. That is true about energy and false about the thing that actually binds.
The constraint is current, not capacity. A house draws power through a service rated in amps, and during an outage everything must pass through the battery's controller instead. What that controller passes continuously is a published specification, and it is smaller than most people assume.
Two manufacturers we read rate their backup controller at 160 amps continuous. Both sheets also carry a 200 amp figure, which is the busbar and overcurrent protection rating rather than the continuous throughput. Those are different specifications and only one of them describes what your house can draw.
So a critical load panel is not a compromise imposed by a small battery. It is how the architecture works. The circuits you want during an outage move into a separate panel that the system can energise on its own, and the rest of the house stays on the main panel, which is dead until the grid returns.
The manufacturers are explicit about the limit. One installation guide forbids whole-home backup outright for one of its configurations. Another manufacturer offers a whole-home option and still excludes the circuits it designates as sheddable, which are the large 240-volt loads. In at least one case, "whole home" means the whole home minus the things that use the most power.
Where the transfer switch actually lives now
Older backup arrangements used a separate automatic transfer switch: a box whose only job was to disconnect the house from the grid and connect it to the backup source. Modern battery systems have absorbed it.
One manufacturer describes its controller as containing an "inbuilt neutral forming transformer, microgrid interconnection device, automatic transfer switch, and a panel board". Four functions in one enclosure, one of which is the transfer switch and another of which is the small panel the backed-up circuits live in.
Another manufacturer names three separate islanding devices depending on the configuration.
Two practical consequences follow. First, when you are quoted a battery you may also be being quoted a controller, a subpanel and the labour to move circuits between panels, and those are real line items rather than padding. Second, the controller is a single point through which all backup power flows, which is why its continuous rating matters more than the battery's capacity for deciding what can run.
The islanding function is the safety half of this and it is not optional. A system that kept exporting during an outage would energise lines that utility crews may be working on. That is why a grid-tied system without this equipment shuts down entirely when the grid fails, which surprises homeowners during their first outage and is the system working correctly.
The equipment, named properly
- Critical load panel
- The subpanel holding the circuits that stay live during an outage. Also called a backup loads panel, a protected loads panel or an essential loads panel, all meaning the same thing.
- Automatic transfer switch
- The device that disconnects the house from the grid and connects it to the backup source. On modern battery systems it is inside the controller rather than a separate box.
- Microgrid interconnection device
- The equipment that lets your system form an island: a small self-contained grid running on your property while the utility grid is down. It is also what stops you exporting into lines crews may be working on.
- Islanding
- Operating disconnected from the utility grid. Deliberate islanding is what backup is. Unintentional islanding is a serious safety hazard, which is why a grid-tied system without this equipment shuts down entirely in an outage.
- Load shedding
- Automatically dropping circuits when demand approaches the controller’s limit. Some systems do this in a defined order, some simply trip. Worth knowing which yours does before you find out.
- Continuous rating
- The current the controller passes indefinitely, as distinct from the busbar or overcurrent protection rating printed alongside it. The continuous figure is the one that governs your outage.
Choosing the circuits, which is the actual decision
Everything above is architecture. The decision you make is which circuits go in the panel, and it is worth doing deliberately because moving them later means an electrician and a permit.
The obvious candidates are cheap in current and expensive to lose. A refrigerator or freezer, some lighting, the router and modem, phone charging, and a furnace fan if you heat with gas, since a gas furnace that cannot run its blower heats nothing.
The hard ones are the large 240-volt loads: electric water heating, electric ranges, air conditioning, electric vehicle charging. These are what a whole-home configuration typically sheds first, and each is a candidate for a deliberate decision rather than an assumption.
The special cases are the ones nobody thinks of until they matter, and they are worth listing because each one has caught somebody out. A well pump, without which there is no water at all. A sump pump, whose failure during the storm that caused the outage is the classic sequence. Medical equipment. A septic pump. Any of these can move the whole decision, and none of them appears on a standard list.
There is also a sizing trap in the opposite direction. A panel with too few circuits is the obvious mistake and a panel with too many is the quieter one, because every backed-up circuit is a route by which something can be switched on during an outage and drain the battery faster than you intended. A household that backs up its entire kitchen will discover this the first time somebody uses the kettle out of habit. The circuits you choose are also the temptations you leave available, and there is an argument for keeping the list genuinely short and using an extension lead for anything occasional.
And the constraint is surge as well as continuous draw. Motors demand far more current starting than running, so a well pump or an air conditioning compressor can be within the panel's continuous rating and still fail to start. We cover the surge question in more detail alongside the generator comparison.
One structural point is worth understanding before you start choosing. Circuits, not appliances, are what move. A single kitchen circuit may carry the refrigerator and four countertop outlets; a lighting circuit may cover two rooms and a hallway. So backing up the fridge may mean backing up whatever else shares its circuit, and separating them means an electrician rewiring rather than simply relabelling a breaker. This is why the exercise is cheaper at design stage than afterwards, and why an installer walking your panel with you is worth the hour it takes.
The way to do this properly is a list before a design. Write down what must work, find the nameplate figures for anything with a motor, and give that to the installer. A system sized against your list is a different product from one sized against a capacity number.
What typically goes where, and why
| Load | Usually backed up? | The consideration |
|---|---|---|
| Refrigerator and freezer | Yes | Modest continuous draw, expensive loss, and a compressor surge worth checking |
| Lighting circuits | Yes | Very small draw. Usually a subset rather than every circuit in the house |
| Router, modem, phone charging | Yes | Negligible draw and disproportionate value during an outage |
| Furnace or boiler fan | Usually | A gas furnace that cannot run its blower produces no heat. Small load, large consequence |
| Well pump | Decide deliberately | No water without it, and a large starting surge. The most common source of an unpleasant surprise |
| Sump pump | Decide deliberately | Fails during exactly the storm that caused the outage |
| Air conditioning | Often not | Large continuous draw and a large compressor surge. May exceed what the controller passes |
| Electric range, electric water heating | Usually not | Large 240-volt loads. These are what whole-home configurations shed first |
| EV charging | Usually not | Large and deferrable, though a vehicle can be a reason to want backup rather than a load to back up |
Analysis by HyreSolar, drawing on the manufacturer controller ratings and backup configuration restrictions cited below.
The two bold rows are the ones to decide rather than default. Both are cheap to include at design stage and expensive to add later, and both have starting surges that need checking against the product’s published capability.
What the code says about the equipment itself
Battery equipment brings its own code provisions, and the residential code text is readable where the electrical code is not.
There is a threshold. The residential provisions on energy storage apply above one kilowatt-hour, so anything a homeowner would call a home battery is inside them.
Location is restricted. The provisions specify where storage may be installed rather than leaving it open, which is why the answer to "can it go in the basement" is a code question rather than a preference.
Spacing and clearances are specified. Three feet between units, and three feet of clearance from doors and windows. Multiple units on a wall are not simply a matter of fitting them.
And fire separation may be required, with the provisions specifying five-eighths inch Type X gypsum board where separation is called for.
Manufacturer restrictions sit on top of these, and can be stricter. One manufacturer's installation guide bans habitable-space installation outright with its own clearance figures. The code sets a floor; the manufacturer's instructions are also part of the requirement, and your local official applies both.
One thing we are not giving you is electrical code article text. The relevant articles on optional standby and stand-alone systems are paywalled and we did not read them. Where this page describes what equipment does, it comes from manufacturers' installation guides, which state what the manufacturer requires rather than what the code does.
How to get this right at quote stage
- 1 Write the list before you see a design
What must work during an outage, in order of importance. This is the specification, and a proposal produced without it is sized against a product rather than against your house.
- 2 Get the nameplate figures for anything with a motor
Well pump, sump pump, air conditioning compressor, large freezer. The locked rotor amperage is on the nameplate and it is what determines whether the thing starts at all.
- 3 Ask for the controller’s continuous rating, not the busbar rating
Two manufacturers publish 160 amps continuous alongside a 200 amp busbar figure. Only one of those describes what your house can draw during an outage.
- 4 If you are offered whole-home backup, ask what it excludes
One manufacturer forbids it for a configuration and another excludes its sheddable circuits by design. Get the excluded list in writing before you accept the phrase.
- 5 Ask where the panel and the battery will physically go
Code restricts storage locations, requires spacing from other units and clearance from doors and windows, and may require fire separation. Manufacturer instructions can be stricter. This is settled before installation or it is settled expensively afterwards.
- 6 Ask what happens when a backed-up load exceeds the controller
Some systems shed loads, some trip. Knowing which, and in what order, tells you what your outage actually looks like rather than what you hope it looks like.
- 7 Add a circuit you have not thought of
A single outlet in a useful place costs almost nothing at design stage and covers the thing you did not anticipate. Everyone who has been through a long outage has one of these.
- 8 Ask what the panel looks like when the grid is up
The backed-up circuits are live all the time, fed from the grid through the controller in normal operation. Knowing that the second panel is not a dormant thing that wakes in an emergency, but a panel your house uses daily, makes its continuous rating easier to think about and explains why it sits between your service and those circuits at all times.
Method and limitations
What was read
Manufacturer installation guides and data sheets for the controller architecture, the 160 amp continuous rating against the 200 amp busbar and overcurrent protection rating, the integration of the transfer switch and microgrid interconnection device, and the whole-home backup restrictions.
The residential code provisions on energy storage systems, for the one kilowatt-hour threshold, the location restrictions, the three foot spacing and door and window clearances, and the fire separation specification.
What we did not read, and what follows
The electrical code articles on optional standby systems, stand-alone systems, load calculations and electric vehicle supply equipment are all paywalled and none was obtained. This page therefore describes what manufacturers require in their installation guides, which is authoritative for their equipment and is not the same thing as stating what the code requires.
Two electrical code provisions appear in our research only as quoted inside a manufacturer's whitepaper. We have not used them on this page, because a manufacturer quoting a code provision is not the same as reading it.
What is judgement rather than sourcing
The table of what typically goes in a critical load panel is our analysis rather than a finding from a source, and the page says so. What is sourced is the controller rating that constrains it, the manufacturer restrictions on whole-home configurations, and the code provisions on the equipment itself.
We give no figure for how many circuits a given battery supports, because it depends on the loads on those circuits rather than on their number, and no source supports a general answer.
Questions
What is a critical load panel?
Why can a battery not just power the whole house?
Some products offer whole-home backup. Is that real?
Do I still need a separate transfer switch?
What should I put in the panel?
Can my well pump run on battery backup?
Where can the battery be installed?
Can I add circuits to the panel later?
Written and audited by
HyreSolar Research
Primary-source research, data analysis and fact checking
We are a research desk, not a sales floor. We read the statute, the tariff, the code section, the federal filing or the manufacturer data sheet ourselves, and we publish the figure with the document it came from and the date we retrieved it. Where a number cannot be traced to a primary source, we publish the shorter page and say what we could not verify. That rule has cost us whole sections, and it is the reason the rest can be trusted.
- 160
- primary sources read and cited
- 220
- figures with a retrieval date
- 115
- federal and state government sources
- 66
- researched pages published
How this desk works
- Primary sources only. Statutes from the legislature’s own publishing system, federal data from the agency that collects it, code text from the adopted edition, manufacturer claims from the data sheet. We do not cite an article that cites a source; we go and read the source.
- Every figure carries its provenance. A named document and the date we retrieved it, so you can check it and so you know how old it is. Retrieval dates are not decoration: an EIA rate from May is a different fact from an EIA rate from August.
- We publish what we could not verify. Every research page carries a section naming the things we tried to establish and could not, and why. A paywalled standard, a state website that refused the request, a manufacturer that publishes no figure at all.
- We separate measurement from modelling from our own reasoning, and label which is which on the page. A laboratory measurement, an assumption inside a modelling tool and our own inference are three different kinds of claim and they are never presented as one.
- We do not sell solar, and we take no payment for placement, ranking or a favourable mention. Nobody buys a position on this site.
Data as of Manufacturer installation guides and code text read on 3 September 2026. Authorship on this site is organisational: the analysis belongs to the desk rather than to a named individual, and we do not publish credentials we do not hold. Our editorial policy sets out how we source, date and correct what we publish.
Sources & retrieval dates
- Enphase IQ System Controller 3 Quick Install Guide and IQ Battery 5P data sheet — Source for the controller containing an inbuilt neutral forming transformer, microgrid interconnection device, automatic transfer switch and panel board; for the 160 amp continuous rating against the 200 amp busbar and overcurrent protection rating; and for the prohibition on whole-home backup in one configuration. Retrieved 3 September 2026.
- FranklinWH installation guide and system user manual — Source for the 160 amp continuous controller rating and for the finding that its whole-home backup configuration excludes the circuits it designates as sheddable. Retrieved 3 September 2026.
- 2024 International Residential Code, section R330, Energy Storage Systems — Source for the one kilowatt-hour threshold below which the provisions do not apply, the permitted installation locations, the three foot spacing between units and three foot clearance from doors and windows, and the five-eighths inch Type X gypsum board specification where fire separation is required. Retrieved 3 September 2026.
Not sure what should be on your backup panel?
Send us the list of what must work and the nameplates for anything with a motor. We will tell you what the surge requirements are and what the product you are quoted can actually carry.
HyreSolar is an independent analysis and matching service. We are not an installer, lender or utility. When a reader asks to be introduced, installers may pay us a referral fee. That fee never buys ranking, scores or placement in research. Our editorial policy sets out the rules.