HyreSolar

Solar services

Solar panel installation

The nine stages between a signed contract and a system you may switch on, who handles each one, and what to ask before you sign.

Updated September 3, 2026

Get Solar Quotes Solar installation costs

Written by HyreSolar Research Desk Primary-source research and fact checking

The short answer

A home solar installation is mostly paperwork. The crew may be on your roof for a few days, but the project runs for weeks or months, because a building permit, an inspection and the utility’s permission to operate all have to come through before you may switch the system on.

30 business days: PG&E’s standard for permission to operate, counted from the last of three documents PG&E Electric Rule 21, effective 29 August 2025
10–30% hidden financing fees the CFPB found built into some solar loan prices CFPB Solar Financing Issue Spotlight, August 2024

What should you know first about solar Panel Installation?

Know who does the work

The seller may not be the installer; ask whose license the permit is pulled under.

Get the cash price

Financing fees can sit inside a loan price without a line of their own.

Check the roof first

An array can outlast an older roof covering, and taking it off later is a separate paid job.

Get solar options for a new installation

Free, with no obligation. A person at HyreSolar reads it and gets back to you. Matching with solar professionals is not live yet.

What does a solar installation involve?

A solar installation is four jobs in one project: structural work on the roof, electrical work at your service panel, a permit application with your city or county, and an interconnection application with your utility.

Companies split those jobs differently. Some do all four with their own staff. Others subcontract the roof work, the electrical work, or both.

The split matters because your warranty, your liability and your contact when something leaks all depend on which company did which part.

What can stop a project before it starts?

Three conditions can delay or rule out a design before any equipment is ordered.

Roof condition

A covering near the end of its life should be replaced first. See solar and roof replacement.

Shade

Trees and neighboring buildings change the design, the equipment and the output. A good assessment measures shade across the year instead of judging it by eye.

Service panel capacity

An older electrical panel may not accept a solar connection without an upgrade, which is its own permit and its own cost.

Who is actually on your roof?

Residential solar can have a sales layer that is separate from the installation layer. A salesperson may represent a dealer, who assigns the job to an installer, who subcontracts the roof attachments.

That chain is not a problem in itself. It becomes one when you do not know about it, because the workmanship warranty is owed by whoever did the work.

Ask whose license the permit is pulled under, and who employs the people on the roof. Who actually installs your solar covers the arrangements.

Which kind of installation fits your property?

The same stages apply to each. What changes is the structure the panels sit on.

How solar Panel Installation runs, step by step

01
Site assessment

Someone measures the roof, the shade, the electrical panel and your usage. A proposal made without this is a sales estimate, not a design.

02
System design

Array layout, panel and inverter models, string or panel-level electronics, and how the system ties into your service panel.

03
Contract and financing

The money decisions are locked in here. Read the cash price, the financed price and any fee between them, and the escalator on a lease or PPA.

04
Permitting

The installer submits plans to your city or county. Timelines vary widely by jurisdiction, and this is where quiet delays build up.

05
Interconnection application

Filed with your utility alongside the permit. Some utilities require a study before they approve.

06
Installation

Racking, panels, conduit, inverter and the tie-in at the service panel. For a home array this takes days, not weeks.

07
Inspection

Your jurisdiction inspects the electrical and structural work. A failed inspection means a correction, not necessarily a redesign.

08
Permission to operate

The utility signs off and you may switch the system on. Under PG&E’s tariff, its 30-business-day clock starts only once the inspection clearance and two other documents arrive.

09
Monitoring and handover

The monitoring portal is set up in your name. Check it in the first month, not the first year.

What moves the price of solar Panel Installation?

No single national figure describes solar Panel Installation. These are the variables that separate two quotes for it.

FactorEffect on a solar Panel Installation quote
System sizeSet by your usage and your usable roof, not by what you would like to spend.
EquipmentPanel efficiency and inverter type. Microinverters and optimizers cost more than a string inverter and can earn it back on a shaded or complex roof.
Roof complexitySteep pitch, several roof planes, tile, or anything needing extra fall protection adds labor.
Electrical workA service panel upgrade or a long conduit run from roof to panel is a real line item.
Permit and interconnection feesSet by your jurisdiction and your utility, not by the installer.
FinancingThe CFPB found hidden financing fees of 10 to 30% built into some solar loan prices. Ask for the cash price as well.

Sourced figures sit in the solar installation costs; check a quote line by line with the proposal analyzer.

What to ask before you sign for solar Panel Installation

Whose license is the permit pulled under, and who employs the installation crew?
What is the cash price, before any incentive and before any financing fee?
Which panel and which inverter, by model number?
What does the workmanship warranty cover, for how long, and who honors it if your company closes?
What happens to the array if I need a new roof in eight years?
How long have permits and interconnection taken in my jurisdiction on your recent jobs?

Your inquiry

Tell us about your home

Nothing goes to a solar professional unless you agree.

Free, with no obligation: a person reads it and gets back to you. Matching is not live yet, so this is not a quote.

Get Solar Options

If you have done your research and want to speak with a solar professional, HyreSolar can help you explore available options.

Your details

Questions

How long does a solar installation take?
The work on the roof takes days for a home array. The whole project takes weeks to months, because design, the permit, the inspection and the utility’s permission to operate come first. PG&E’s tariff alone allows 30 business days for its final review.
Can I use the system as soon as the panels are up?
No. You need permission to operate from your utility, which comes after your jurisdiction has inspected the work. Switching on a grid-tied system before that can breach your interconnection agreement.
Do I need to replace my roof first?
If the covering is near the end of its life, replacing it first avoids paying later to take the array off and put it back. If the roof is newer, no. A roofer’s written estimate of remaining life settles it.
Does solar work during a power outage?
A standard grid-tied system shuts down in an outage so it cannot send power into lines that crews are repairing. Keeping power during an outage needs a battery and an inverter set up for backup.

Written and audited by

HyreSolar Research

Primary-source research, data analysis and fact checking

We are a research desk, not a sales floor. We read the statute, the tariff, the code section, the federal filing or the manufacturer data sheet ourselves, and we publish the figure with the document it came from and the date we retrieved it.

Where a number cannot be traced to a primary source, we publish the shorter page and say what we could not verify. That rule has cost us whole sections, and it is why the rest can be checked.

160
primary sources read and cited
228
figures with a retrieval date
115
federal and state government sources
66
researched pages published

Authorship on this site is organizational: the analysis belongs to the desk rather than to a named individual, and we do not publish credentials we do not hold. Our editorial policy sets out how we source, date and correct what we publish.

Sources & retrieval dates

PG&E Electric Rule No. 21 (Advice 7692-E), Effective 29 August 2025. Source for the definition of permission to operate, the three documents the utility must receive, and the thirty-business-day processing standard. Retrieved 2 September 2026.
CFPB, Solar Financing Market Issue Spotlight, Consumer Financial Protection Bureau, August 2024. Source for the hidden financing fee range of 10 to 30 percent built into some solar loan prices. Retrieved 2 September 2026.

This page on solar Panel Installation is general and varies by location, utility tariff, building code, roof and your own circumstances. It is not tax, legal or engineering advice. HyreSolar is an independent information site: we do not install, finance, service or inspect solar systems, and we do not supervise or warrant anyone who does.