Solar removal and reinstall checklist

For a reroof under existing panels: before, during and after.

Sources checked October 22, 2026 · 2 primary and dated sources

Written by HyreSolar Research Desk Primary-source research; not legal or financial advice

The short answer

This solar removal and reinstall checklist lists every step of a reroof with solar in order: permissions before work, removal and storage, the new roof, reinstallation and recommissioning.

It matters because the warranties sit with different parties. Manufacturer warranties such as Enphase’s exclude the labor of removing and reinstalling equipment, and a leased system belongs to the provider, which must agree first.

Record production before and after so any loss can be traced to the job.

Get quotes to check against this list

Before work starts

  • Confirm ownership

    Leased or PPA: get the provider’s written approval and its approved contractor list.

  • Read the workmanship and manufacturer warranties

    Ask who may remove the system without voiding them; get authorization in writing.

  • Get quotes from a solar contractor for detach and reset

    Sourced price ranges on removal and reinstall cost.

  • Agree who coordinates roofer and solar crew

    One contract, or two with a written schedule.

  • Check whether a permit or utility notice is needed

    Many jurisdictions require an electrical permit for reinstallation.

  • Photograph and log production for two weeks

    Your baseline.

During the job

  • System shut down by the solar contractor per the inverter manual
  • Panels labeled and stored flat, protected, on site or insured off site
  • New flashing and mounts installed with the new roof, not reused

    Ask for the flashing product and the roofer’s penetration warranty.

  • Rails and wiring inspected and replaced where damaged

After reinstallation

  • Inspection passed, if a permit was pulled
  • Monitoring shows every panel or string reporting
  • Production back to baseline for similar weather
  • Written warranties from the roofer (roof) and solar contractor (reinstall)
  • Provider notified the job is complete (leased systems)

When you are ready

Ready to explore solar for your home?

If you have done your research and want to speak with a solar professional, HyreSolar can help you explore available options.

Free, with no obligation: a person at HyreSolar reads your request and gets back to you about it. Matching with solar professionals is not live yet, so this is not a quote, and nothing is shared with anyone until you agree.

Keep learning

We reply to every inquiry. Nothing is passed on to anyone you have not asked us to contact.

Questions

Who should remove solar panels for a reroof?
A licensed solar contractor, ideally one your warranty or lease provider approves. Roofers generally should not disconnect solar equipment.
Does the manufacturer warranty pay for removal?
Not usually. Enphase’s warranty, for example, excludes the labor of uninstalling and reinstalling products.
Should I reroof before going solar instead?
If the roof is near the end of its life, yes: it avoids paying for this job later. See our roof-before-solar check.

Sources and retrieval dates

  1. Enphase Energy Limited Warranty, IQ Microinverters , labor exclusion; 90-day notice Retrieved 22 October 2026.
  2. Sunrun Inc., Form 10-K for fiscal 2025 , transfer-on-sale terms Retrieved 22 October 2026.

This page explains how solar contracts and consumer rules usually work and links the documents it relies on.

It is general information, not legal, tax or financial advice; your own contract and your state’s law decide your case.

For a dispute, speak to a lawyer licensed in your state or your state attorney general’s consumer office. HyreSolar does not install, finance, lease or sell solar.