Questions this calculator answers
- How long does solar interconnection take?
- It depends on your utility, so we publish no national figure. Deadlines are set state by state and utility by utility, and a stale benchmark could push you to escalate at the wrong time. Your utility’s interconnection handbook gives the review target that governs your queue; this tool compares against it.
- Who is holding up my project?
- One of three organizations, depending on the stage. The utility holds application review and permission to operate. Your installer holds the gap between approval and installation. The local building department holds inspection. Three of the six stages are not the utility’s, so chasing the utility is not always the right move.
- My application has been under review for weeks with no response. What should I do?
- First, ask whether it was accepted as complete: an application returned for missing information can look submitted while no review clock runs. If it was accepted and the stage has passed your utility’s published target, send a written request for a status and a date, copied to your installer.
- The system is installed and inspected. Why can I not switch it on?
- Because permission to operate has not been issued. Until it is, you have no agreement permitting you to export, and energizing anyway can put you in breach of your interconnection agreement and can complicate a later claim. This stage can include a bidirectional meter change, which is a separate field visit with its own scheduling.
- Can I make the utility go faster?
- Not by asking: utilities process applications in queue order. You can remove reasons for delay: confirm the application is complete, answer any information request the same day, and check your installer supplied everything asked for. A missed tariffed deadline is a matter for your state regulator.
- Why does the tool ask me for the target instead of knowing it?
- The alternative is a 50-state table we cannot retrieve or keep current. Interconnection rules live in state regulator dockets and individual utility handbooks. An out-of-date deadline could mislead your decision to escalate, so we ask you to look up your own.
- Does a battery change the interconnection?
- It can. Storage can trigger additional review, a different application path, or an engineering study. If a battery was added to your design after the application was submitted, expect the clock to restart rather than continue.
- What if my installer goes out of business mid-process?
- The interconnection application is generally in your name with the installer acting as agent, so it does not disappear with them, but somebody has to take over the submissions, the responses and the inspection. Our piece on what to do when your installer closes covers the practical steps.
- Does the PTO date matter after the fact?
- Yes. It can be the start date for equipment warranties and the date your export tariff attaches to, and in some states it determines which version of a net metering rule applies to you. Keep the letter.
Sources and methodology
Figures dated September 5, 2026. Last reviewed by the HyreSolar research desk, which writes and checks every tool on this site.
- How solar interconnection works (HyreSolar Research Desk, retrieved September 5, 2026). Our own explanation of the six-stage sequence and what the utility reviews at each gate.
- Permission to operate: what it is and when it is issued (HyreSolar Research Desk, retrieved September 5, 2026). Source for the statement that export is not permitted before PTO and that the PTO date commonly starts equipment warranties.
- Rule 21: Generating Facility Interconnection (California Public Utilities Commission, retrieved September 5, 2026). An example of a state-adopted interconnection rule with published review timeframes. Named to show what a reader should look for in their own state, not used as a national benchmark.
Related solar tools
- Hosting capacity screen Your system against the feeder headroom on your utility’s map.
- Service panel upgrade check Screens an inverter size against the NEC 120% busbar rule.
- Contract red-flag checker Counts the expensive clauses to ask about before you sign.
Your real numbers come from a proposal drawn for your roof, your usage and your utility. Tell us about your home: a person reads it, and nothing goes to a solar company until you agree.