HyreSolar

Quick answer

Distributed Energy Resource A distributed energy resource (DER) is a small power source or storage device connected to the local distribution grid or installed behind a customer’s meter, such as rooftop solar, a home battery, an EV charger or a smart thermostat in a demand-response programme.

The opposite is a large central power plant on the high-voltage transmission grid. A home solar system is a DER, and the paperwork your utility sends you may call it one.

Quick facts

The key facts about distributed energy resource, with sources:

FERC’s typical size range
1 kW to 10,000 kW 1
Where it sits
On the distribution system, a subsystem of it, or behind a customer meter 1
Includes
Storage, intermittent and distributed generation, demand response, energy efficiency, thermal storage, EVs and their chargers 1
Key federal rule
FERC Order No. 2222 (17 September 2020) 1
Interconnection standard
IEEE 1547-2018 2
US small-scale solar output, 2025
About 93 million MWh (EIA estimate) 5
Narrower term
Distributed generation (DG): DERs that generate electricity

Key takeaways

  • A DER is any small device on the local grid that makes, stores or saves electricity. Rooftop solar is the most common one.
  • FERC describes DERs as usually 1 kW to 10,000 kW, sitting on the distribution grid or behind a customer’s meter 1.
  • Your utility may call your solar or battery a “DER facility” or “DG facility” on interconnection forms.
  • Inverters for home DERs are tested to IEEE 1547, the US standard for connecting DERs to the grid 2.
  • FERC Order No. 2222 lets groups of DERs sell into wholesale markets, but programmes depend on your region.
  • Before you add solar or a battery, ask your utility about export limits, hosting capacity and any battery programme.

What counts as a distributed energy resource

The word “distributed” means spread out. Instead of one big plant far away, many small sources sit close to where people use power. The US Department of Energy gives rooftop solar panels, backup batteries and emergency diesel generators as examples 3.

FERC’s definition is wider than generation. It also counts things that change when or how much power you use. That list includes electric storage, demand response, energy efficiency, thermal storage, and electric vehicles with their chargers 1.

So a DER does not have to make electricity. A water heater that a utility can switch off at peak times can count. So can a smart thermostat enrolled in a programme. What they share is size, location on the local grid, and the ability to change the flow of power.

Sources: [1] [3]

Where a home DER sits on the grid

  1. Central power plant → high-voltage transmission lines
  2. Substation → local distribution lines (where DERs connect)
  3. Your meter → behind it, your grid-tied solar and any battery
  4. Surplus from your DER → flows to neighbours on the same distribution line

How a home DER works with the grid

Power from your roof meets your home’s needs first. When the panels make more than the house is using, the extra flows out through your meter. It then feeds homes on the same street. When the panels make less, the grid fills the gap.

The inverter is the traffic controller. An inverter is the box that turns the panels’ direct current (DC) into the alternating current (AC) your home uses. IEEE 1547-2018 sets the rules it must follow when it connects to the grid 2. These include how it responds to voltage and frequency changes.

One rule matters most for safety. If the grid goes down, a grid-tied system must stop sending power out.

DOE explains that an “islanded” section of grid could damage equipment or injure line workers, so many solar systems are set to detect islanding and disconnect 3.

That is also why plain grid-tied solar goes dark in a blackout.

Sources: [3] [2]

Types of DER you might own

Categories follow FERC’s list [ferc]. Whether a utility pays for each one depends on its programmes.
TypeHome exampleWhat it does for the grid
Distributed generationRooftop solar system, small windMakes power close to where it is used
Electric storageHome batteryStores power and releases it later
Demand responseSmart thermostat or water heater in a utility programmeCuts or shifts use when the grid is strained
Energy efficiencyInsulation, efficient heat pumpLowers demand all the time
Electric vehiclesEV and its chargerA large load that can be timed; some can also send power back
Thermal storagePre-cooling or pre-heating a home or tankMoves energy use to a different hour

Distributed energy resource vs distributed generation

Utilities use both terms. Distributed generation is the generating subset of DERs.
Distributed generation (DG)Distributed energy resource (DER)
CoversEquipment that produces electricity near where it is usedAnything small on the local grid that produces, stores or reduces demand for electricity
Home examplesRooftop solar, a small wind turbineRooftop solar, a home battery, an EV charger, a smart thermostat in a demand-response programme
Where you meet the wordUtility tariffs and interconnection pages, e.g. Georgia Power’s "Distributed Generation" website 6; Santee Cooper’s Distributed Generation Rider DG-25 7FERC rules, grid planning, IEEE 1547 and newer interconnection documents 2
OppositeCentral generationBulk power system resources on the transmission grid

Example: one street’s worth of DERs

An illustration with round numbers, not data for any real street. FERC’s Order 2222 lets regional grid operators set a minimum aggregation size of no more than 100 kW 1. Here is how home batteries could add up to that size.

StepMathResult
Battery output per home (example)Assume each battery can discharge 5 kW5 kW each
Homes needed to reach 100 kW100 kW ÷ 5 kW20 homes
Homes needed if the market minimum were lower, say 50 kW50 kW ÷ 5 kW10 homes

No single home could take part alone. A group run by an aggregator can. The real minimum, and whether a programme exists at all, is set by your regional grid operator and utility. Check a battery’s actual output on its data sheet; our battery power rating entry explains the number.

Where "DER" shows up for a homeowner

  • Your interconnection application: utilities often call your solar or battery a "DER facility" or "DG facility". Georgia Power’s residential summary refers to a customer’s DER facility on its Distributed Generation interconnection page 6.
  • Inverter spec sheets: the IEEE 1547-2018 listing shows the inverter meets the US standard for connecting DERs to the grid 2.
  • Tariff names: South Carolina’s Santee Cooper credits rooftop solar exports under its Distributed Generation Rider DG-25, with hourly netting 7.
  • Battery programmes: offers to pay you for letting the utility or an aggregator draw on your battery at peak times are DER programmes.
  • Hosting capacity maps: some utilities publish maps showing how much new solar each local line can take. Our hosting capacity lookup points to them.

Benefits and limits of DERs

Benefits

  • Power is made right where it is used, so less is lost on long lines 3.
  • Many small sources spread risk; one failure does not take out a region.
  • With a battery or microgrid, a home or community can keep key loads running in an outage 3.
  • Groups of DERs can earn money in some wholesale markets under Order 2222 1.

Limitations

  • A plain grid-tied solar system shuts off in a blackout for safety 3.
  • Each local line can only take so much new solar before upgrades are needed 4.
  • Utilities set export limits, size caps and fees that differ by territory.
  • Payment programmes for batteries are patchy and change often.

Hosting capacity: why your line may be full

The National Laboratory of the Rockies (formerly NREL) defines hosting capacity as the amount of distributed solar a distribution system can add “before control changes or system upgrades are required” 4. In plain words, it is how much more rooftop solar a local line can take as it is.

It is not a hard wall. The lab notes that hosting capacity grows as upgrades are made 4. It depends on inverter settings, system size, where you sit on the circuit and what other DERs are nearby.

If your line is near its limit, the utility may ask for a study, a smaller export, special inverter settings, or an upgrade. That can add time to your project. Ask early, before you sign.

Sources: [4]

What drives the cost of adding a DER

We do not publish a price for a DER, because it covers everything from a thermostat to a large solar array. For rooftop solar, see our solar cost guide and cost per watt breakdown.

A few costs are specific to being a DER on the grid. Your utility may charge an application or study fee. A full line can lead to upgrade costs. Some tariffs add a monthly fixed charge for solar customers; the fixed charge lookup helps you find yours.

Equipment life drives long-run cost. Inverters and batteries carry their own warranties, often shorter than the panels’. Read each warranty on the product data sheet rather than relying on a sales claim.

How a home DER gets connected

Steps vary by utility. This is the usual order for rooftop solar or a battery.

  1. A licensed installer designs the system and checks your utility’s size limit and export rules.
  2. The installer files an interconnection application with the utility, often naming the system as a DER or DG facility.
  3. The utility reviews it. A screen checks hosting capacity on your line; a fuller study may follow if the line is busy.
  4. You or the installer get a building or electrical permit from the local building department.
  5. A licensed electrician or installer does the work. You do not wire anything yourself.
  6. The local inspector checks the work against the electrical code.
  7. The utility may swap or reprogram your meter, then grants permission to operate.

Our interconnection timeline tool shows where delays usually happen.

Keeping a DER working

  • Check your monitoring app monthly. A sudden drop to zero often means the inverter has tripped; see monitoring showing zero.
  • Keep inverter firmware current. Utilities can ask for new grid settings under IEEE 1547 2, and updates usually come through the installer.
  • Tell your utility before you add panels or a battery. A change in size is a new interconnection review.
  • Keep your interconnection agreement and permission-to-operate letter. You will need them if you sell the home.

Warning signs and when to call a pro

  • The system makes power during a grid outage without a battery and transfer switch. That is unsafe; call your installer at once.
  • The inverter shows repeated grid voltage or frequency faults. Your line may be near its limit; ask the utility and installer.
  • Someone offers to connect a system without utility approval. Unapproved systems can be disconnected and may break your tariff terms.
  • A battery programme contract lets a third party drain your battery fully. Check how much reserve you keep for outages.
  • Any burning smell, buzzing or heat at the panel or inverter. Shut off at the labelled disconnect only if safe, and call a licensed electrician.

Safety rule

Never connect solar, a battery or a generator to home wiring yourself. A licensed electrician and utility approval are required, because back-fed power can injure line workers.

The rules: FERC Order 2222 and IEEE 1547

On 17 September 2020 the Federal Energy Regulatory Commission issued Order No. 2222. It requires the regional grid operators that run organised wholesale markets to let DERs compete in those markets alongside power plants, by grouping them into aggregations.

One home battery is far too small to sell into a wholesale market. Hundreds of them, managed together by an aggregator, can be. Each grid operator’s rules must set a minimum aggregation size of no more than 100 kW.

The order also lets a DER that is already in a utility retail programme take part in wholesale markets, with limits to stop the same service being paid for twice.

Order 2222 covers only organised wholesale markets, and grid operators phase it in on their own timelines. Much of the Southeast has no such market, so do not assume a programme is open to you.

The technical rule is IEEE 1547-2018, the standard for connecting and operating DERs with the grid 2. Your state commission and utility decide how it applies, along with size limits and export credit. Local electrical inspection follows the code your state adopted.

Sources: [1] [2]

Common misconceptions

Myth A DER must make electricity.
Reality FERC’s list also counts storage, demand response, energy efficiency and EVs 1.
Myth My solar keeps my lights on in a blackout.
Reality Grid-tied solar is designed to disconnect when the grid fails 3. Backup needs a battery or other islanding equipment.
Myth Order 2222 means my utility must pay me for my battery.
Reality It applies to organised wholesale markets, through aggregators, on each region’s timeline 1.
Myth Hosting capacity is a fixed cap.
Reality The lab says it is not a hard limit and rises as upgrades are made 4.

DER terms in South Carolina, Georgia and Virginia

In South Carolina, Santee Cooper’s DG-25 rider pays $0.0415/kWh for net excess, nets hourly, and pays a monthly net credit of $50 or more by check 7.

Georgia Power limits residential renewable DER facilities in its RNR export programme to 10 kW 6. Virginia allows residential net metering up to 25 kW on investor-owned utilities 8.

All of these describe the same kind of rooftop system under different names.

When the DER label matters to you

Most homeowners never need the term. It matters in these cases:

  • You are filling in an interconnection form. Answer the DER questions with your installer; the system size and inverter model must match the permit.
  • You are buying a battery. Ask the utility whether it runs a battery or demand-response programme, and what control it would take.
  • Your utility mentions a hosting capacity limit. Ask what a smaller system or export limit would allow.
  • You want backup power. Plan a battery or hybrid solar system rather than plain grid-tied solar.
  • Next step: compare installers who handle the paperwork for you through Get Solar Options.

Questions about distributed energy resource

Is rooftop solar a distributed energy resource?

Yes. Rooftop solar is the most common DER: small generation connected behind a customer’s meter on the distribution grid. DOE lists rooftop panels first among its DER examples, and EIA estimates US small-scale solar made about 93 million megawatt-hours in 2025. Your utility will usually call it a DER or DG facility on paperwork.

What is the difference between DER and DG?

Distributed generation (DG) means small equipment that generates power. DER is the broader category that also includes batteries, EV chargers, demand response and energy efficiency. So all DG is DER, but not all DER is DG. A home battery is a DER that is not generation.

What does FERC Order 2222 mean for homeowners?

It lets aggregators bundle many small DERs, such as home batteries, so they can sell services into organised wholesale markets. It does not force your utility to pay you.

Whether a programme is open to you depends on your region, its grid operator’s timeline and your utility. Many areas, including much of the Southeast, have no organised market.

What is a DER aggregator?

A company that enrols many small DERs and operates them together as one resource. Grouped, they can meet market size and performance rules that no single home could meet alone.

Under Order 2222 the minimum group size can be no more than 100 kW. Read any contract for how much control they get over your battery.

Is a home battery a DER?

Yes. FERC names electric storage as a DER type. A battery can store solar power for evening use, provide backup, and in some areas join a utility or aggregator programme. Your utility treats adding one as an interconnection change, so it needs review and a licensed installer.

Is an electric vehicle a distributed energy resource?

Yes. FERC includes electric vehicles and their charging equipment in its DER definition. An EV is a large load you can time, for example charging overnight. Some newer vehicles can also send power back, but that needs special equipment and utility approval.

What is hosting capacity?

Hosting capacity is how much more distributed solar a local power line can take before the utility needs control changes or upgrades. The National Laboratory of the Rockies notes it is not a hard limit and rises as upgrades are made. If your line is near its limit, expect a study or export limit.

What standard must a DER inverter meet?

In the US, IEEE 1547-2018 sets how DERs connect and operate with the grid. Inverters listed to it can ride through small grid disturbances and respond to voltage and frequency changes. Your utility and state decide which settings to use, and your installer programs them.

Why does my solar turn off during a power outage?

Because it is a grid-tied DER designed to disconnect when the grid fails. Power fed into a dead line could injure line workers or damage equipment. To keep power in an outage you need a battery or a hybrid system that can island your home safely.

Sources

  1. FERC, Order No. 2222 fact sheet: A New Day for Distributed Energy Resources (17 Sep 2020, Docket RM18-9-000), retrieved .
  2. IEEE, Standard 1547-2018 for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces, retrieved .
  3. US DOE Solar Energy Technologies Office, Solar Integration: Distributed Energy Resources and Microgrids, retrieved .
  4. National Laboratory of the Rockies (formerly NREL), Advanced Hosting Capacity Analysis, retrieved .
  5. US EIA, Electric Power Monthly Table 1.1.A (small-scale solar photovoltaic generation), retrieved .
  6. Georgia Power, Behind-the-Meter Interconnection Summary for Residential Customers (rev. 15 Aug 2025), retrieved .
  7. Santee Cooper, Distributed Generation Rider DG-25, retrieved .
  8. Code of Virginia §56-594 (net energy metering), retrieved .

Expert review

Written by the HyreSolar Research team. Not yet reviewed by an outside expert. We say so rather than imply a review that has not happened; see our editorial policy.

How the numbers were checked: The DER definition, size range and Order 2222 terms are from FERC’s own fact sheet.

DER examples, islanding and microgrid points are from DOE SETO; hosting capacity from the National Laboratory of the Rockies; small-scale output from EIA Table 1.1.A. Tariff usage is from the Georgia Power summary, the Santee Cooper rider held in sc-local/facts.js (retrieved 5 Oct 2026) and Va.

Code §56-594. The aggregation example uses round illustrative inputs, labelled as such.

Suggest a correction. We fix errors and say what changed.